Tunnel excavation in Berlin

Scope of Work

A 6,4 km expansion of the Berlin Underground bumped into trouble when ground water started pouring in during tunnel excavation under the Minna-Cauer-Strasse. Work had to be interupted, and the project put on hold. To keep moisture penetrating from below at bay, this part of the construction site was flooded.

That’s how we ended up with our underwater excavator in Berlin. It’s a typical example of a task where a land based excavator can be converted to a useful subsea tool.

There was a lot of grout piles inside the tunnel due to grout injection performed in the past. The remote-controlled excavator was used to cut grout and soil with a drumcutter in order to dredge and pump the material out of the pit.  Tunnel water was of very high turbidity, and there was practically no visibility (>5cm) – a fact that made the task even more complex.

Location

Berlin, Germany

Main Spread

20Te

Tooling

Cutter drum, Xcentric ripper, long suction nozzle, HP jetting

Water Depth

~20m

Duration

360 days

Year

2017/18

Planning Phase

Various underwater excavation works was required; dredging/removal of soil, demolition of grout blocks, silt suction/removal and removal of horizontal and vertical blinding layers with various material strength. The variety in material made the preparation phase demanding in terms of selection the most proper tooling. Several site visits and substantial hours of testing was performed prior to the operation to optimize the project execution.

Challenges
  • Various soil/ layers to be removed
  • Sand
  • Mud/clay
  • Grout piles (Grid, 1,5 x 2m)
  • Horizontal and vertical steel and plastic pipes
  • Reinforced concrete blinding layer 
  • GEWI uplift anchors (not to be damaged)
  • 0-5cm visibility
Specific Tooling

A 20Te Scanmachine spread and various tooling was shipped to Berlin 

  • Extra long suction nozzle (2m)
  • Xcentric ripper
  • Drum cutter
  • Telescopic arm
  • 3D sonar to deal with the limited visibility

Other Projects

Optimize positioning of a drilling rig

Optimize positioning of a drilling rig

Rockdump redemial to support the footprint of a drilling rig on two locations, according to design criteria’s from DNV to fulfill stabilisation in the foundation and minimise seabed disturbance. Debris removal & pipe uncovering

Installation of an AC power and optical cables system

Installation of an AC power and optical cables system

Planning PhaseOnce the substation jacket was installed, a rock dumping vessel performed the scour protection around the jacket, but there was still a need for rock installation inside the jacket.Challenges Strong current & Low visibility Precise placement of rock...