Optimize positioning of a drilling rig

Optimize positioning of a drilling rig

Image Caption: Picture from onshore testing of Log grapple and 2m Tilt bucket Planning Phase Project specific challenges were highlighted in the planning phase. Based on the significant volume of mass to be processed, we had learned from the 2018 campaign that the...
Seabed preparation at Heimdal

Seabed preparation at Heimdal

Image Caption: Simulating pre- and post-dredging at one location Planning Phase Challenges The dredging was to be carried out near existing subsea assets right outside the 100 meters safety zone of the respective platforms, so planning and safety aspects had to be...
Tunnel excavation in Berlin

Tunnel excavation in Berlin

Planning Phase Various underwater excavation works was required; dredging/removal of soil, demolition of grout blocks, silt suction/removal and removal of horizontal and vertical blinding layers with various material strength. The variety in material made the...
Rock installation to optimize positioning of a drilling rig

Rock installation to optimize positioning of a drilling rig

Image Caption: Picture from onshore testing of new grab Planning Phase In the planning phase we went through the scope of work to highlight project specific challenges. Based on the large volume, the conclusion was that a traditional ejector setup was not ideal as...
Rock installation inside substation jacket

Rock installation inside substation jacket

Image Caption: 15Te Scanmachine (top) and Scancrawler Planning Phase Once the substation jacket was installed, a rock dumping vessel performed the scour protection around the jacket, but there was still a need for rock installation inside the jacket. To solve this...